Draper's road list runs to 2027, and one entry's label does not match its construction date
Draper's published capital lists put the Lone Peak Parkway widening and new turn lanes at 11400 South and 700 East in 2027, and give Fort Street a 2028 label next to a 2027 construction date.
Automated reporting, from the sources cited below. How this paper is made.
DRAPER — The City Council's Nov. 17 study session carried two capital improvement updates, one for parks and one for major roads, in the 5:30 p.m. session that preceded the 7 p.m. business meeting 12. The agenda lists them as "Parks CIP Update - Rhett" and "Major Roads CIP Update - Scott" 2. The city's recap of the meeting records no vote on either item; the business session's recorded outcomes are the consent agenda, local consent for a special use permit for Wasatch Product Development LLC, and Ordinances 1745 and 1746, each approved 4-0, and the meeting adjourned at 7:34 p.m. 1.
The money the lists draw on sits in the Capital Improvement Projects Fund. The budget document in the council's Aug. 18 packet puts that fund at approximately $35,185,600, most of it for projects previously approved and funded, and adds $1,775,000 for new projects in fiscal 2026-27: $950,000 for park projects and maintenance and $825,000 for infrastructure improvements 5.
**Lone Peak Parkway and 11400 South**
The road list is the presentation Public Works Director and City Engineer Scott Cooley gave the council on July 7, 2026 3. It schedules the widening and realignment of Lone Peak Parkway between 12300 South and 12650 South for construction in 2027 and records funding of "around $850,000" in partial corridor preservation money and "$3 Million in additional federal funding" secured 3. The same slide lists "Property Condemnation" among the project's elements 3.
Acquisition reached the council on Aug. 4. Resolution 26-38 authorized the filing of an eminent domain action to acquire real property for the Lone Peak Parkway project, and the council adopted it on a unanimous roll-call vote after a public hearing at which, the minutes state, no one came forward 5. The minutes record Cooley telling the council that planned improvements required right-of-way, and JD Kesler of Parsons Behle, the city's outside counsel, telling the council there had been negotiation with four different ownerships 5. The resolution recites that notice was mailed to the property owners and that the council heard the item on Aug. 4 6.
A second project on the 2027 list is shared with Sandy. The July presentation describes dual left-turn lanes in both the eastbound and westbound directions on 11400 South at 700 East, federally funded and built in conjunction with Sandy City, also listed for 2027 3.
**Fort Street's two dates**
Fort Street is listed under the heading "Fort Street – Pioneer to 13200 South (2028)" 3. The bullets under that heading state that construction is planned for 2027 and will impact Draper Days, and describe the work as widening Fort Street to match the city's master plan, with curb, gutter, sidewalk, storm drain and asphalt widening and reconstruction 3. The presentation gives no explanation for the two dates, and the council took no action on the schedule Nov. 17 13.
**What is scheduled for this year**
The 2026 projects in the same presentation are, in its words: Pioneer Road resurfaced from 700 East to just west of 1300 East, with storm drain upgrades and sidewalk, curb and gutter improvements from 700 East to Fort Street; dual northbound left-turn lanes at the 146th South and Minuteman intersection; curb, gutter and a continuous sidewalk along the west side of 700 West, with storm drainage work; a sidewalk gap on Manfield Way between Somerdowns Court and Carraway Lane, and sidewalk on both sides of Canyon Point Road from Lone Hill Drive to Ember Drive; an expansion of the City Hall parking lot adding up to 32 stalls; the Suncrest detention pond, rerouting storm drainage from Detention 85 to a larger pond; replacement of two Suncrest pressure-reducing valves; widening and signal upgrades at Bangerter Highway, 13800 South and 150 East; 30,000 cubic feet of stormwater storage and a larger pipe at 1700 East; sidewalk repair in Zone 4; and citywide crack and slurry seals 3.
**Parks and trails**
Parks and Recreation Director Rhett Ogden's July 7 update lists the department's projects with budgets and status 4. Jenson Farm Park carries a $215,000 design figure, $1,400,000 for Phase 1, $1,300,000 for Phase 2 including a $650,000 county grant, and $2,000,000 for Phase 3, which the slide shows under construction with completion anticipated in July 2026 4. The Porter Rockwell Trail crossing of 1300 East on the existing UTA bridge is budgeted at $180,000, was awarded to Lyndon Jones Construction, and was scheduled to start construction by July 2026 with completion in the fall 4. The Bonneville Shoreline Trail Spring Hollow bridge replacement is budgeted at $100,000, half of it a Utah Outdoor Recreation grant, was awarded to Avid Trails, and was scheduled for construction in summer 2026 with completion in the fall; the replacement bridge is 40 feet long and 5 feet wide against an existing 12-foot span 4.
The Sunrise Station Park expansion, budgeted at $100,000, was listed for construction in fall 2026 4. Phebe Brown Trail Phase 2, 0.32 miles of paved trail along the East Jordan Canal from Carlquist Drive to Corner Canyon Creek, carries a $600,000 budget and a timeline of "TBD – pending direction to P&R Department" 4.
Seven items on the same slides had no city funding when the presentation was given and were described as requests in the fiscal 2027 budget: the $1,200,000 development of Hidden Canyon Park, with playground, picnic shelters, paths, grass and a restroom; $150,000 for design of the Honeybee Park and East Jordan Canal trail, comprising a loop trail in Honeybee Park, a canal crossing, approximately one mile of paved trail within the East Jordan Canal corridor from 11400 South to 11800 South and park improvements on the south park area, with the slide stating that construction is estimated to be $1.7 million and that the city may pursue grant funding once preliminary design is completed; automatic gates at the Orson Smith and Potato Hill trailheads, an estimated $60,000; new signs at all parks and trailheads, an estimated $150,000; an extension of the Canyon Hollow Trail from the upper Corner Canyon Road to the Peak View Trail, an estimated $40,000; and flyover crossings at the Vertigo and Levitate trail intersection and at the Maple Hollow and Ann's Trail intersection, an estimated $25,000 each 4. The presentation does not state whether any of them was funded; the fiscal 2027 budget document lists the new park money as a single $950,000 line for projects and maintenance 45.
**The business session**
The two ordinances took up 1.67 acres at 12430 S. 700 East, rezoning the property from RA1 and RA2 to R4 7 and approving a development agreement that limits it to five lots 8. This paper reported the vote and the agreement's terms on Nov. 18 8. The planning commission had forwarded both applications with a 5-0 recommendation on Nov. 12 8.
Two more land-use hearings are set for Dec. 1 at 7 p.m. One would rearrange the split RA1 and RA2 zoning at approximately 999 E. 13200 S to accommodate a future subdivision, noticed by planner Todd Draper 9. The other would rezone approximately 13720 S. 300 East from RA1 to RM1, up to eight dwelling units per acre, amend the land use map from residential low/medium to medium/high density, and amend the development agreement to add four lots to the Concord Farm Lane subdivision, noticed by planner Maryann DeHaven 10.
- https://www.utah.gov/pmn/files/1519607.pdf
- https://www.utah.gov/pmn/sitemap/notice/1123230.html
- https://www.utah.gov/pmn/files/1459047.pdf
- https://www.utah.gov/pmn/files/1459049.pdf
- https://d3n9y02raazwpg.cloudfront.net/draper/ef7cc51e-ea85-11f0-bb28-005056a89546-65652db6-473c-4a32-b019-051002d8279f-1787340200.pdf
- https://draper.granicus.com/services/legistar/download/pdf/4269145/26-38_Resolution_Authorizing_Eminent_Domain_for_Lone_Peak_Parkway_Project.pdf
- https://www.utah.gov/pmn/files/1519369.pdf
- https://southvalleyledger.com/articles/draper-approves-five-lots-at-12430-s-700-east-4-0-with-the-terms-writt-754264
- https://www.utah.gov/pmn/sitemap/notice/1125389.html
- https://www.utah.gov/pmn/sitemap/notice/1125397.html
- https://draperherald.com/articles/draper-council-agenda-lists-roads-parks-capital-project-updates-mwt65dn4
More from this paper
- Corner Canyon's Nafanua Alofipo named 2026 Deseret News Ms. Volleyball
- Draper Park Middle student takes 13th at national junior chef competition
- UDOT warns of up to 40 extra minutes on I-15 and 30 on U.S. 6 this Thanksgiving weekend
- Draper council gives a fragrance maker local consent to use alcohol in its plant
0 comments on Bluesky
Reply on BlueskyNobody has replied to this story yet. Comments live on Bluesky, where anyone can join in.
Comments are hosted on Bluesky and shown here as they appear there. The Ledger keeps no reader accounts, and nothing about your reading; the one thing a reader may leave us is an email address, if they choose to sign up.